T1 - Risk-Based Institutional Evaluation of Trans Sumatera TollRoad Infrastructure Development to Improve Time Performance
AU - Fakhrin, Muhammad Ridho
AU - Riantini, Leni Sagita
AU - Latief, Yusuf
N1 - Publisher Copyright:
© 2023 American Institute of Physics Inc.. All rights reserved.
PY - 2023/12/15
Y1 - 2023/12/15
N2 - Based on the 2015-2019 RPJMN data, the realization of toll road infrastructure development in Indonesia experienced a delay of 49% or 904 km of the total plan. One of the major causes of delays in development is caused by institutional factors. The case study taken in this research is the construction of the Trans Sumatra Toll Road (JTTS). The purpose of this research is to identify the institutional forms, functions, roles, duties, and responsibilities of each stakeholder and the risks that occur in the Trans Sumatra Toll Road Infrastructure Development. Risk analysis is implemented on functions, roles, duties, responsibilities of each existing stakeholder and is carried out at the Funding Stage, Technical Planning Stage, and Construction Implementation Stage in JTTS. This research is conducted by collecting data through a questionnaire survey, then processed using statistical methods, such as homogeneity, data adequacy, validity, and reliability test, continued with risk assessment based on a risk matrix. The results of this study are the evaluation and development of institutional functions in risk-based JTTS development can improve time performance and minimize delays in the construction process.
AB - Based on the 2015-2019 RPJMN data, the realization of toll road infrastructure development in Indonesia experienced a delay of 49% or 904 km of the total plan. One of the major causes of delays in development is caused by institutional factors. The case study taken in this research is the construction of the Trans Sumatra Toll Road (JTTS). The purpose of this research is to identify the institutional forms, functions, roles, duties, and responsibilities of each stakeholder and the risks that occur in the Trans Sumatra Toll Road Infrastructure Development. Risk analysis is implemented on functions, roles, duties, responsibilities of each existing stakeholder and is carried out at the Funding Stage, Technical Planning Stage, and Construction Implementation Stage in JTTS. This research is conducted by collecting data through a questionnaire survey, then processed using statistical methods, such as homogeneity, data adequacy, validity, and reliability test, continued with risk assessment based on a risk matrix. The results of this study are the evaluation and development of institutional functions in risk-based JTTS development can improve time performance and minimize delays in the construction process.
KW - Institutional
KW - Risk Management
KW - Time Performance
KW - Toll Road
UR - http://www.scopus.com/inward/record.url?scp=85180354115&partnerID=8YFLogxK
U2 - 10.1063/5.0187713
DO - 10.1063/5.0187713
M3 - Conference contribution
AN - SCOPUS:85180354115
T3 - AIP Conference Proceedings
BT - AIP Conference Proceedings
A2 - Sambas, Aceng
A2 - Sukono, null
A2 - Vaidyanathan, Sundarapandian
PB - American Institute of Physics Inc.
T2 - 2nd International Conference on Applied Sciences, Technology, Engineering and Mathematics, ICASTEM 2021
Y2 - 2 November 2021 through 3 November 2021
ER -