TY - JOUR
T1 - Development of a risk-based strategy implementation of a full pre-financed contractor scheme (CPF) in toll road projects to improve time performance
AU - Ichsan, Mohammad
AU - Isvara, Wisnu
AU - Handibyanto, Jodi Noor
AU - Muhammad, Farras Ammar
N1 - Publisher Copyright:
© 2024 The Author(s). Published by Informa UK Limited, trading as Taylor & Francis Group.
PY - 2024
Y1 - 2024
N2 - Several reasons underlie the use of Contractor Full Pre-Financed (CPF), which provides a much higher return opportunity than a standard payment contract system or the Monthly Certificate (MC). The case study in this research is one of the toll road construction projects in Indonesia that uses the CPF scheme. This study uses qualitative risk analysis to determine the dominant risk, quantitative risk analysis using the PERT distribution method to measure the impact of adding days due to the dominant risk on the critical path and produce a strategy to reduce the added days value due to risks in toll road projects with the CPF scheme. Strategy development is carried out to reduce the value of inherent risk to become a residual risk. The potential value of additional project completion time due to dominant risk is 30.68%–38.33% of the initial duration of the project. Through the development of strategies for each critical path activity, the potential added value of project completion time due to dominant risk can be reduced to 11.45%–16.73% of the initial project duration.
AB - Several reasons underlie the use of Contractor Full Pre-Financed (CPF), which provides a much higher return opportunity than a standard payment contract system or the Monthly Certificate (MC). The case study in this research is one of the toll road construction projects in Indonesia that uses the CPF scheme. This study uses qualitative risk analysis to determine the dominant risk, quantitative risk analysis using the PERT distribution method to measure the impact of adding days due to the dominant risk on the critical path and produce a strategy to reduce the added days value due to risks in toll road projects with the CPF scheme. Strategy development is carried out to reduce the value of inherent risk to become a residual risk. The potential value of additional project completion time due to dominant risk is 30.68%–38.33% of the initial duration of the project. Through the development of strategies for each critical path activity, the potential added value of project completion time due to dominant risk can be reduced to 11.45%–16.73% of the initial project duration.
KW - business, management and accounting
KW - Civil, environmental and geotechnical engineering
KW - Contractor Full Pre-Financed (CPF)
KW - PERT analysis
KW - qualitative risk analysis
KW - quantitative risk analysis
KW - risk management
KW - Sanjay Kumar Shukla, Edith Cowan University, Australia
KW - time performance
KW - toll road projects
KW - transportation engineering
UR - http://www.scopus.com/inward/record.url?scp=85185338370&partnerID=8YFLogxK
U2 - 10.1080/23311916.2024.2307212
DO - 10.1080/23311916.2024.2307212
M3 - Article
AN - SCOPUS:85185338370
SN - 2331-1916
VL - 11
JO - Cogent Engineering
JF - Cogent Engineering
IS - 1
M1 - 2307212
ER -